Adding an Arrow in MultiQuant™ Software to Display the Expected Retention Time during Peak Review


Date: 10/29/2020
Categories: MultiQuant Software

0 Votes
   Print    Rate Article:

For research use only. Not for use in diagnostic procedures.


Answer

In MultiQuant™ software, an arrow can be added to the peak review chromatogram window to represent the expected retention time. To do this, right click within the peak review pane and select Options from the list. A Peak Review Options popup window will appear. Check the option Mark Expected RT with Arrow under the Appearance tab. Then select OK. 

User-added image

Once this option is selected, an arrow should show for expected retention time under the chromatogram. 

User-added image